Readers Write: Don’t count on 3rd track being completed on time

stevenblank

There is still more to “LIRR Main Line expansion construction begins” (Rebecca Klar – June 28). 

That same week, Newsday reported in “According to “LIRR Third Track First Phase” by Alfonse A. Castillo published on June 24 that the completion date for this $2.6 billion project has slipped from 2022 to early 2023.

This delay of several months (in less than six months after contract award) will be the first of what I predict to be many more during the four or more years it will take to complete this ongoing project. 

Remember you read it here first in the always informative and cutting edge Great Neck News and Blank Slate publications.  Only 10 of the 50 project components will be initiated over the coming 18 months.  

The success of starting full 24 trains per rush hour peak along with reverse commuter service for Long Island Rail Road East Side Access to Grand Central Terminal is directly dependent upon the Main Line Third Track also being completed by December 2022.  Earlier this year, MTA officials promised that the most recent construction recovery schedule was guaranteed and written in stone for service to begin by December 2022. 

Just like all the other previous promises going back to the original 2009 completion date, this now appears to have crumbled to dust. 

Don’t be surprised if the final completion date for LIRR Main Line Third Track with 40 more project components to be initiated in coming years slips several months or a year from the original promised December 2022 date to December 2023 or later.  

Now that work will commence on Main Line Third Track, when will the LIRR share a real detailed project budget that includes the estimated costs for each of the 50 project components? 

What about a detailed project schedule that would reveal the start and end date along with interim milestones for each of the fifty project components.  A detailed project schedule should include the overall project critical path. 

This information reveals the relationship between each of the 50 project components. 

If one or more of the overall project critical path should fall behind, it could trigger a domino effect impacting other project schedules.  This could result in further delays to the overall project final completion date.   

The LIRR has a very sophisticated yearly annual schedule for management of capital improvement projects, along with assignment of Force Account (LIRR employees), track outages and procurements (purchasing of capital items) to ensure maximum efficient utilization of resources.   

Does the LIRR have enough workers and scheduled track outages to support Main Line Third Track along with East Side Access to Grand Central Terminal, Positive Train Control, Jamaica Station Capacity Improvements, Ronkonkoma Double Tracking, new Ronkokoma Storage Yard and LaGuardia Air Train Willets Point Station (just to name a few) along with all the other numerous annual state of good repair and safety projects and programs to meet Main Line Third Track budget and schedule?     

Will there be any slow work zone areas resulting in train schedule service delays as the first ten projects begin to be underway?  Will this result in adding several minutes to the travel time for commuters on some trains?

How much work over the next four years will be performed evenings, overnight and on weekends? 

We already now know that work for the Covert Avenue street crossing will run 24 hours per day five days per week for one year. 

How many of the other 49 projects within Main Line Third Track will require the same amount of time or more?  Main Line Third Track is an incredibly complex project to perform 100% of the work within and adjacent to two active tracks. 

It is like a doctor attempting to perform open heart surgery on a jogger who is running a 26-mile marathon. 

There are 194-weekday and 152-weekend trains serving riders on the Huntington/Port Jefferson, Oyster Bay, Ronkonkoma and Babylon to Speonk branches. This does not include additional LIRR work trains, freight trains and movements of non-revenue passenger trains not in service. 

How many times per hour will work stop when a train passes by? 

Don’t be surprised when you learn that a significant portion of construction work ends up taking place evenings, overnight and on weekends when there is less activity on the Main Line.  

Each grade crossing elimination may require several weekend track outages resulting in partial to full suspension of Main Line service. 

Will there be any need for future 24/7 shuttle bus service between Jamaica and Mineola or Hicksville?  Costs for substitute bus service could easily run into the millions over the project’s construction.

What will the future impact of any access improvements to the Belmont Park Islanders Arena LIRR Station be to Main Line Third Track schedule? 

How would the potential installation of new interlockings west of the Floral Park Station be coordinated with Main Line Third Track? 

This would be necessary to provide direct access east of Belmont Park versus traveling westbound to Jamaica followed by changing to another train so riders can double back east to the Belmont Park Islanders Arena Station.

When will the MTA/LIRR share this information with commuters, residents, taxpayers, transit advocates, elected officials and the media to build credibility for this project?

Based on past experiences and history with other major projects such as LIRR East Side Access to Grand Central Terminal, don’t count on Main Line Third Track being completed by December 2022 and now early 2023 as promised by the MTA LIRR.  

Larry Penner

Great Neck

(Larry Penner is a transportation historian and advocate who previously worked in 31 years for the US Department of Transportation Federal Transit Administration Region 2 NY Office.) 

Editors Note: Aaron Donovan, deputy communications director for the Metropolitan Transportation Authority, responded to the letter’s posting online, saying there has been no slippage or delay of the third track’s completion date. Donovan said Penner was “confusing the opening of service on the third track, which is slated for December 2022, with formal conclusion of the contract, which is slated for early 2023 while the contractor closes out their work and completes punch-list items.”